References

Lalitpur Power Generation, India

Training programs on operation of coal handling plant, ash handling plant, and ESP

SESI was hired to provide specialized training to operation and maintenance staff. So far, training in the following areas has been conducted: 

  • Operation of coal handling plant and ash handling plant
  • Operation and maintenance of ESP›Boiler tube failure and case studies
  • Burner management system / FSSS
  • C&I in power station (for operation engineers)
  • Valve and pump maintenance›Boiler and auxiliary maintenance
  • Training in remaining areas will be provided August to December 2017

Project facts

Installed capacity3 x 660 MW (supercritical)
CustomerLalitpur Power Generation Company Limited
Execution of SESI servicesMay 2017 - December 2017